How To Integrate MS Project with Timesheet

Follow these steps to integrate Microsoft Project with Standard Time®.  (scroll down for the video)

  1. Start by choosing File, Projects.
  2. Right-click on a project and choose Microsoft Project Integration Wizard
  3. Navigate to your MPP file
  4. Finish the Wizard

MS Project will open the MPP file and pull down your tasks into Standard Time®.  You won’t see them in the timesheet right away.  There is one step you must take first.

Click the Project Tasks tab to see the new tasks from the MPP file.  At the far right, you will see a columns labeled Timesheet.  Check the boxes for each task you wish to see in the timesheet.  Any task without this checked will not show up in the timesheet.

Now that you have integrated the timesheet with MSP, you can send your ‘Actual’ hours back.

Choose View, Refresh Project Tasks.  That will open a dialog that lets you send your timesheet hours to MSP.